More Evasions and Avoidance

The Council appear to have erased the breach of Condition 5 from the records and the MP had talks with UK Docks in the spring of 2017 but appears to have been given short shrift.

Work starts on Sixth Frame

59 11/08/17
Misinformation
Email to Cllr Anglin about the planning breach of 2001 passed to Customer Advocacy Their response about a second shed is a complete misrepresentation.
60 06/09/17
Misinformation
Response to email of the 29th March about MP meeting UK Dock’s representatives.
Introduces events that took place after the meeting.
61 06/09/17
Class of its own
MP told: The previous issues relating to the boat yard have in fact now been looked at by the Local Government Ombudsman and they found no issue with the yard or anything relating to its development. Unfortunately, the Ombudsman’s decision cannot be re-visited.
62 12/12/18
Encoded
Misinformation
Council solicitor repeats 3 items of misinformation given to the Ombudsman, width, height and sequence of events .
63 09/04/19
Letter
not even
acknowledged
to the Monitoring Officer asking what is the planned height?
but no answer!
64 09/04/19
Email not answered
to the Monitoring Officer asking if there had been a retrospective planning application you their shed. It only needs to be yes or no but it needs to be in writing.
but no answer!
65 19/06/19
Email
not even
acknowledged
to the Monitoring Officer informing him that a Council Solicitor quoted three misrepresentations given to the Ombudsman in defence of a Councillor.
NO answer!
66 17/09/19 To Building Control
Laid off to planning and they ignored it!
67 25/09/19 Reappraisal – Planning Breaches
Information copied to the Monitoring Officer
68 05/12/19 Dishonesty at the Town Hall
Ignored!
69 12/12/19 Check on misleading note from Monitoring Officer
At least we may get an answer from her.
70 19/12/19
Denial
That no retrospective application received is
confirmed.
Still no admission that the shed is 3m taller than permitted.
71 08/01/20
More than evasions and denials.
Gave home phone number to Mr Palmer <palmerk@parliamant.uk> but he does not accept that any of this occurred and attempts to in his desire to get the count of evasions, demials and repetition to zero.
Into 2020: Mr Palmer appears to be an agent of those who wish to discredit the office of the MP for South Shields. He does not wish the issue of the Council misleading the Ombudsman to be raised in Parliament.

70 Evasions, Denials or Silences

To this, one can add the list of emails:-

  1. given by Ms Hayton – December 2019 (11);
  2. given to Ms Abbott – April 2021 (23).

It appears that the Council have known since September 2013 that the shed was, and still is, about 3m  taller than planned because they would not answer any questions about the height.
The Planning Manager conceded in February 2014 that it was indeed too tall but his replies could be interpreted to mean that there was no breach in planning control and they then use a corrupted complaints procedure to drive the matter through to the Ombudsman where by misrepresentation and misinformation they ensured that the complaint wa not upheld.

They then quoted the Ombudsman to put off any further enquiries; from the Press and MPs. UK docks than extended the shed onto foundations laid in 2001 and after it became obvious to all that they had lied to the Ombudsman, they needed to change  tack and now say: It remains the case that all complaints procedures relating to this matter have been exhausted both internally within the Council and externally.

This still overlooks the fact that the shed is now nearly a meter wider, 3m taller and 6m longer than permitted!

EoP